Prior Lake Outlet Channel Repairs: Bank Erosion

Bank erosion repair work has been completed along the channel. Maintenance for vegetation reestablishment is an ongoing project.

Completed

Project Location: Prior Lake Outlet Channel (PLOC)

Status Details:

Bank erosion repair work has been completed along the channel. Maintenance for vegetation reestablishment is an ongoing project.

A major flood event occurred in 2014 leading to the highest recorded water elevation, 906 feet, on Prior Lake since the outlet system was first installed. During the 2014 flood the outlet channel functioned properly, while continuously receiving water from the elevated Prior Lake. Water rushed through the channel at a rate and volume never experienced before. This extreme water velocity coupled with the duration of rainfall events caused significant damage throughout the channel. Trees fell, sediment was distributed, and over 20,000 feet of bank erosion occurred.

The Prior Lake-Spring Lake Watershed District worked with the Federal Emergency Management Administration (FEMA) and was approved for federally-financed repairs. Repair projects along the outlet channel included:

  • Tree and woody debris removal
  • Streambank stabilization
  • Culvert replacements
  • Sediment removal
  • Image slide of One of three culverts which was replaced.

    One of three culverts which was replaced.

  • Image slide of Damage to outlet channel before tree removals.

    Damage to outlet channel before tree removals.

Benefits

  • Restored 20,000 feet of bankshore

Related Documents

Partners

Federal Emergency Management Administration

PLOC Cooperators (Shakopee Mdewakanton Sioux Community, City of Prior Lake, City of Shakopee)